How Much Does a Road Diet Cost?

page1image4101323168page1image4101323440

As roadway funding becomes more and more limited and improvement projects face fierce competition, public agencies search for cost-effective, practical solutions to meet safety and operational needs of all users. Road Diets are a low-cost countermeasure with proven safety benefits for both motorized and non-motorized users. A Road Diet reallocates roadway space to better meet current user needs. This configuration is an inherently low-cost solution, butagencies can reduce project costs even further by combining Road Diets with other programs, such as pavement overlays or restriping.

Right-of-Way Savings

Expanding a street to include safety and multimodal improvements like bicycle lanes, a two-way left-turn lane (TWLTL), and wider shoulders is usually not a practical solution. Streets often exist in constrained urban or suburban settings, making the acquisition of additional right-of-way expensive and complex, if not outright impossible. Road Diets reallocate roadway space within the existing footprint, eliminating the need for purchasing property, lengthy environmental studies, complex design plans, and expensive construction. Moreover, Road Diets are one of the least expensive solutions for accommodating additional modes such as bicycles or transit vehicles.

Societal Cost Savings

All roadway crashes take a toll on society. Even minor crashes can require costly repairs, while the worst crashes can impact individuals financially for a lifetime. Additional societal costs include infrastructure repair, lost employee time at work, and insurance premium increases. In 2013, the U.S. Department of Transportation (USDOT) updated its estimated costs to society incurred by fatal, injury, and property damage only (PDO) crashes.Research has shown that the typical four- to three-lane Road Diet reduces the total number of crashes by 19 – 47 percent, resulting in significant cost savings.2

Maintenance Savings

Road Diets can reduce overall maintenance costs, especially when they decrease the number of travel lanes. Alternative facilities such as TWLTLs, bicycle lanes, medians, and wider shoulders receive less wear than travel lanes, and therefore require less effort to maintain and repair. Additionally, agencies may experience some cost savings during winter months if there are fewer driving lanes to plow during snowstorms.

Example of a Road Diet

page1image4101604144 page1image4101604416 page1image4101604688 page1image4101605216 page1image4101605424 page1image4101605696 page1image4101605968 page1image4101606240 page1image4101606512 page1image4101606848 page1image4101607120 page1image4101607392 page1image4101607664 page1image4101607936 page1image4101608208 page1image4101608480 page1image4101608752 page1image4101609280 page1image4101609616 page1image4101604896 page1image4101610336 page1image4101610608 page1image4101610880 page1image4101611152 page1image4101611424 page1image4101611696 page1image4101611968 page1image4101612240 page1image4101612512 page1image4101612784 page1image4101613056 page1image4101613328

BEFORE

AFTER

“A Road Diet costs our city tens of thousands of dollars versus a reconstruction project that costs millions.”

Norm Steinman, Charlotte DOT

$9,197,370

$5,454,040

$2,446,500

$965,724 $432,276

$27,592 $6,500

K A1 A2 B1 B2 C O Fatality Injury PDO

USDOT Automotive Crash Cost Estimates

page1image4101642720 page1image4101642992 page1image4101643264 page1image4101643536 page1image4101643808 page1image4101644080 page1image4101644352 page1image4101644688page1image4101645488

  1. 1  U.S. Department of Transportation. Memorandum to Secretarial Officers and Modal Administrators from Polly Trottenberg, Under Secretary for Policy. February 28, 2013.

  2. 2  Evaluation of Lane Reduction ‘Road Diet’ Measures on Crashes. FHWA Report No. FHWA-HRT-10-053. Washington, D.C. 2010.

page1image4101670928 page1image4101671792 page1image4101672064 page1image4101684576 page1image4101684784 page1image4101685056

safety.fhwa.dot.gov/road_diets

page2image4190354256 page2image4190148016 page2image4190201584IET

Project Cost Savings

Although a stand-alone Road Diet is relatively inexpensive, agencies can reduce project expenses even further by coordinating the Road Diet with regularly scheduled resurfacing work. Within these projects, Road Diets add only a nominal expense to the overall project costs but provide a large benefit that ultimately achieves the project’s end goal.

The table below illustrates how coupling a Road Diet with a resurfacing project can reduce costs more than 50 percent compared to a stand-alone Road Diet. The example converts a 4-lane undivided 5000ft long roadway section into two travel lanes, a TWLTL, and two bicycle lanes.

4-lane to 3-lane Conversion Cost (Stand-Alone vs. During Resurfacing Project)

Item

         

Comments

Lane Line Eradication

LF

15,000

$1.50

$22,500

$0

No resurfacing: Assume three lines entire length.
Resurfacing: Not necessary.

Bike Lane Lines Thermoplastic (6”)

LF

10,000

$1.50

$15,000

$15,000

Both: Assume two solid lines entire length.

Travel Lines Thermoplastic (4”)

LF

15,000

$1.00

$15,000

$0

No resurfacing: Assume two solid lines entire length and two striped lines at 50% coverage entire length.

Resurfacing: Included within base project.

Bike Lane Thermoplastic Pavement Marking Symbol

EA

40

$300.00

$12,000

$12,000

Both: Assume one symbol every 250ft each side of road (bike lane).

Bike Lane Sign

EA

20

$250.00

$5,000

$5,000

Both: Assume one sign every 500ft.

Left-Turn Thermoplastic Pavement Marking Symbol

EA

20

$300.00

$6,000

$6,000

Both: Assume one symbol every 250ft (Left-turn arrows).

Maintenance of Traffic (10%)

LS

1.00

$7,500

$7,500

$0

Resurfacing: Included within base project.

Subtotal:

$83,000

$38,000

 

20% Contingency:

$17,000

$8,000

 

Total Estimated Cost:

$100,000

$46,000

 

LF=Linear Foot, EA=Each, LS=Lump Sum

Source:  Incorporating On-Road Bicycle Networks into Resurfacing Projects. FHWA Report No. FHWA-HEP-16-025. Washington, D.C. 2016.

Funding Sources:

Road Diet projects are eligible for funding through Federal programs like the Surface Transportation Program (STP) and Highway Safety Improvement Program (HSIP), as well as other funding mechanisms. For example, Washington State DOT has used funding from such sources as pedestrian and bicycle programs and transit grants. Seattle Department of Transportation (SDOT) has used Safe Routes to School grants for Road Diet installations. SDOT also monitors the city’s road resurfacing projects to see whether streets scheduled for upcoming roadway overlay projects are good candidates for Road Diets, allowing the agency to use annual paving program funds for some installations.3

To learn more about funding opportunities, contact your FHWA State Division office.

Road Diet Informational Guide. FHWA Report No. FHWA-SA-14-028. Washington, D.C. 2014.